A mold can be machined to its drawing and still produce a part that warps, sticks during ejection, or misses an assembly dimension. The drawing, resin, cavity layout, cooling, gate, process settings, and inspection method must be considered together before steel is cut. In injection molding mold making, the first formal sample review is where those decisions are tested on real parts.
This guide follows a custom tool from the initial part package through DFM, mold design, steel selection, CNC and EDM machining, assembly, mold trial, correction, and T1 sample approval. It also identifies the information a buyer should receive at each gate. Shinzoft describes these stages in its injection mold making service; the exact tool concept and approval package should be agreed for each project.
Injection Molding Mold Making: The Process at a Glance
| Stage | Engineering work | Useful output or decision |
|---|---|---|
| 1. Requirements and DFM | Review part function, resin, geometry, tolerances, appearance, volume, and moldability | Approved part revision, CTQ list, DFM comments, and open decisions |
| 2. Mold design review | Define cavities, parting line, gate, runner, vents, cooling, slides, and ejection | Released tool concept and design review record |
| 3. Steel and components | Select tool materials, mold base, inserts, wear parts, and purchased components | Tool specification and purchasing release |
| 4. Machining and finishing | Machine, EDM, grind, fit, polish, and inspect tool components | Measured components ready for assembly |
| 5. Assembly and checks | Fit core and cavity; check slides, ejectors, cooling, and motion | Tool readiness for the first molding trial |
| 6. T1 trial and review | Mold the specified resin, record conditions, inspect parts, and log defects | Labeled samples, measurement results, and action list |
| 7. Correction and approval | Assign root causes, revise tool or process, repeat trials where needed | Approved sample status and controlled next step |
Define the Part Before the DFM Review
The starting package should contain a 3D CAD model and dimensioned 2D drawing with the same revision. Add the intended resin grade or performance requirements, annual and initial quantities, critical-to-quality dimensions, appearance zones, surface finish, inserts, assembly interfaces, test requirements, and any restrictions on gate or ejector marks. If these inputs are missing, the moldmaker has to make assumptions that may later become expensive steel changes.
DFM examines how the part can be filled, cooled, released, and measured. The review should mark wall transitions, ribs, bosses, undercuts, draft, thin steel conditions, side holes, likely weld lines, gate options, ejection risks, and possible distortion. A good comment identifies the affected feature, likely consequence, and a proposed choice: change the part, change the tool concept, test an assumption, or accept a documented risk.
Freeze the agreed part revision before tool design is released. A late change to a sealing surface or hole position may affect cavities, slides, cooling, and inspection fixtures, even when the change looks small in CAD. Shinzoft’s injection molding DFM guide gives more detail on the geometry issues worth resolving before tooling.
Review the Mold Design Before Steel Is Cut
The mold design converts the accepted part model into a repeatable production system. The review should show the mold-opening direction, parting line, number and arrangement of cavities, core and cavity split, runner system, gate type and location, vents, cooling circuits, slides or lifters, ejectors, and replaceable inserts. The proposed machine interface and production volume also influence the design.
Each choice should be tied to a part requirement. A gate can shift a weld line or create a visible vestige. Poorly placed ejectors can deform a cosmetic wall. A slide can make a side hole possible but adds moving surfaces that need alignment and maintenance. Cooling layout affects both cycle time and dimensional stability. Mold-flow analysis can help compare fill, pressure, weld-line, air-trap, and warpage risks when the part warrants it; the result depends on the accuracy of material and process inputs.
Ask for a design review that distinguishes confirmed decisions from open assumptions. The buyer should approve visible marks, parting lines, cavity count, and any change to functional geometry before the tool design is released. Tool ownership, maintenance responsibility, and the intended location of production should also be documented in the commercial agreement.
Select Steel for the Tool’s Actual Duty
Steel selection depends on expected shot count, resin and fillers, surface finish, corrosion risk, part detail, required mold life, repair strategy, and budget. A single tool may use different materials for the base, cavity, core, slides, and wear inserts. Shinzoft lists P20, 718H, S136, H13, and NAK80 among the steels it uses; the correct combination must be selected for the specific tool.
The specification should identify critical components and any heat treatment, hardness, coating, or material certification required by the project. It should also explain where replaceable inserts are sensible. Do not infer a guaranteed shot life from the steel name alone: molding material, geometry, maintenance, processing conditions, and wear areas all matter.
Machine the Core and Cavity with CNC and EDM
After design release, machining creates the mold base, plates, cores, cavities, electrodes, inserts, and moving components. CNC milling is commonly used for accessible surfaces and bulk material removal. Electrical discharge machining, or EDM, can form details that are difficult to mill with a rotating tool, such as narrow recesses or sharp internal features. Wire EDM may be used for suitable through profiles. Drilling, grinding, polishing, texturing, and fitting follow where specified.
The sequence is project-dependent. Some components require rough machining before heat treatment and finish machining afterward; others follow a different route. The engineering goal is to preserve datums and stock allowances through the operations so that core and cavity features align when assembled.
Inspection during injection mold manufacturing should focus on dimensions that affect part CTQs, parting-line sealing, slide travel, insert fit, and cooling connections. A machined component can meet a local dimension while its position relative to the mold datum is wrong. Recording component identity and revision helps prevent mismatched parts during assembly or later repair.

Fit, Assemble, and Check the Tool
Assembly brings together the core, cavity, mold base, slides, lifters, ejectors, cooling connections, and standard components. Toolmakers verify fit and movement, check shutoffs and parting-line contact, and look for interference through the full mold cycle. Cooling circuits should be checked for intended flow and leakage. The tool also needs appropriate venting, access for cleaning, and safe handling arrangements.
At this stage, a dimensional inspection of steel cannot prove the molded part will pass. Resin shrinkage, flow orientation, packing, cooling, and ejection still have to be tested on the press. Assembly checks simply establish that the mold is ready for a meaningful trial and reduce the chance that a mechanical fault prevents sampling.
Run the Mold Trial and Label the T1 Samples
A mold trial puts the assembled tool on an injection molding machine and tests it with the intended material. The naming of trial rounds varies among suppliers. For this article, T1 sample means the first formal molded sample set submitted for engineering review, consistent with Shinzoft’s published process. Confirm this definition and the expected deliverables in the project schedule.
The team should record the actual resin grade and lot, machine, mold and cavity identification, tool revision, drying condition where relevant, setup values, and notable adjustments. Early shots can reveal fill imbalance, short shots, flash, trapped gas, sink, warpage, sticking, or ejection marks. Once a stable process is established, label samples so each part can be related to its cavity and trial condition.
Review the molded part against the approved drawing and functional requirements. Critical dimensions, appearance zones, gate vestige, weld-line location, insert retention, assembly fit, and test performance may all be part of the plan. A sample that looks good can still fail a CTQ dimension; a dimensional report without a known process condition may be difficult to interpret.
Decide What T1 Approval Actually Means
T1 is an evidence gate, not a promise that every tool will be production-ready on its first trial. The buyer and moldmaker should classify each finding as acceptable, requiring process adjustment, requiring tool correction, or requiring a part-design decision. Assign an owner, due date, and verification method to each open issue.
| T1 evidence | Question for the approval meeting | Possible next action |
|---|---|---|
| Labeled samples and trial record | Which cavity, material lot, tool revision, and process produced each sample? | Retain a traceable reference set or repeat an undocumented trial |
| Dimensional report | Do CTQs meet the approved drawing under the agreed measurement conditions? | Check measurement method, process sensitivity, and steel correction options |
| Appearance and defect map | Are marks within approved zones and limit samples? | Adjust venting, gate, finish, process, or design as the cause requires |
| Fit and functional tests | Does the part work in its intended assembly and environment? | Evaluate mating parts, material, geometry, and further validation |
| Open-issue list | Which changes are mandatory before another trial or production release? | Approve an action plan and new sample submission criteria |
Written approval should specify its scope. Acceptance of T1 samples for a fit check is different from final approval for production. The latter may require additional runs, cavity balance, process stability, capability evidence, functional tests, and a production inspection plan. The transition from samples to volume is covered in Shinzoft’s custom injection molding workflow guide.
Correct the Cause and Repeat the Relevant Checks
Tool correction may involve a cavity or core adjustment, insert replacement, vent change, gate revision, cooling change, ejection improvement, or finish work. Before cutting steel again, confirm whether the apparent failure comes from the tool, process, material, part conditioning, or measurement setup. A dimensional error caused by warped samples may not be solved by moving one steel surface.
After each correction, update the tool revision and affected drawings. The next trial should check the changed feature and any connected CTQs. A gate change, for example, can alter weld lines, packing, appearance, and shrinkage in other areas. Keep prior sample reports and issue closures so later reviewers can see why the tool changed.
What Determines the Mold Making Schedule?
Lead time starts with a stable, approved input package. Design review, steel and purchased component availability, cavity count, slides and lifters, hot-runner choice, surface finish, heat treatment, machining capacity, inspection, and trial-machine availability all affect the first T1 date. Engineering change requests and sample corrections can extend the path from T1 to final approval.
Ask the supplier to quote separate milestones: DFM completion, mold-design release, component procurement, machining and assembly, first trial, T1 report, and any planned correction round. The schedule should state what the customer must approve and when. A published lead-time range is only a reference; a project-specific date requires the final part files and tool specification.
Tooling choices also change cost. A higher cavity count or more moving actions can increase the initial tool investment while changing the eventual piece price and capacity. Shinzoft’s tooling and part-cost guide explains those tradeoffs in the broader quotation.
Frequently Asked Questions
What should be approved before mold machining begins?
Approve the part revision, resin requirement, CTQs, cosmetic zones, DFM decisions, and the mold concept. Confirm the cavity count, gate and parting-line locations, major moving actions, tool specification, and any accepted risk.
Why use both CNC and EDM in mold making?
CNC efficiently machines accessible geometry and removes bulk stock. EDM can create details that are difficult to reach or form with a rotating cutter. The combination depends on the cavity shape, steel, finish, tolerance, and tool design.
Does a T1 sample have to pass every requirement?
Not necessarily. T1 establishes what the first formal tool trial produces. The project plan should identify which checks apply at T1, how deviations are recorded, and what must pass before final tool or production approval.
Can a mold be corrected after T1?
Yes. Corrections are common when the trial reveals dimensional, fill, venting, cooling, ejection, or appearance issues. The team should verify the root cause, document the tool revision, and retest affected features.
What is the difference between T1 sample approval and production approval?
T1 approval may mean a particular sample is acceptable for a stated purpose. Production approval requires the agreed evidence that the tool, process, inspection, and output are ready for repeat orders. The acceptance record should state which status has been granted.
What information is needed to estimate the first T1 date?
Provide the 3D model, drawing, resin, part size, tolerances, appearance requirements, expected volume, cavity preference, inserts or undercuts, surface finish, and target sample quantity. The moldmaker can then assess the design, tool complexity, materials, and schedule dependencies.
A Practical Mold Making Decision
A useful mold schedule is built around decisions that can be checked: approved DFM, released tool design, specified steel, inspected components, assembled tool, traceable trial, and a written T1 disposition. That sequence makes a sample delay easier to diagnose and keeps changes tied to their effect on part quality.
To obtain a project-specific mold making schedule, Contact Us with your 3D CAD model, 2D drawing, resin or performance requirement, critical dimensions, expected volume, and target T1 sample date. Shinzoft can review the part and outline the tooling steps and estimated time to the first trial.